From the course: Project Management Foundations: Schedules
Unlock this course with a free trial
Join today to access over 25,300 courses taught by industry experts.
Determine the critical path - Microsoft Project Tutorial
From the course: Project Management Foundations: Schedules
Determine the critical path
- [Instructor] The best way to understand the critical path is to calculate activity dates and total float, so you can determine which activities are critical and why. Total float is the time an activity can move earlier or later, without affecting the project finish date. Total float equals an activity's late finish, minus its early finish. Late finish is the latest date an activity can finish without delaying the project finish date. Early finish is the earliest date it can finish. You also calculate total float using late start minus early start. To see how this works, let's calculate part of the example project's critical path. The first step is called a forward pass, which calculates the early start and early finish for every activity. You start at the project start date, and use durations to determine the early starts and early finishes. Writing chapter seven and eight starts on April 28th. Its duration is two…
Practice while you learn with exercise files
Download the files the instructor uses to teach the course. Follow along and learn by watching, listening and practicing.
Contents
-
-
-
-
-
-
-
What is the critical path?1m 34s
-
(Locked)
Determine the critical path4m 14s
-
(Locked)
Put the critical path to work2m 20s
-
(Locked)
Too many or too few critical tasks3m 37s
-
(Locked)
Lengthen, delay, or split assignments2m 31s
-
(Locked)
Adjust the level of work over time2m 21s
-
(Locked)
Replace overallocated resources3m 30s
-
-
-
-