The Wayback Machine - https://web.archive.org/web/20110521095525/http://www.hornsrev.dk:80/Engelsk/Opstillingen/uk-fundament.htm
 

Constructing a turbine foundation

In the Horns Rev project, Elsam used the so-called "mono-pile" concept, single piles that are driven into the seabed. Pile driving is a fast process, and piles are relatively inexpensive to produce. Geotechnical surveys show that the seabed was made up of sand, and this makes mono-pile foundations particularly attractive.

Mono-pile foundations have also been used for offshore turbines in the Netherlands and Sweden. Similarly, the project�s meteorological tower rests on a mono-pile foundation.

The foundation is designed as a cylindrical steel pipe with a diameter of approx. 4 m and a material thickness of 5 cm. A large, hydraulic ram drives the steel pipes into the seabed to a depth of some 25 meters.

A "mattress" of gravel is placed around the foundation to protect against erosion.

 

The construction phases
 

A "gravel mattress" were arranged to minimise erosion.

- Thickness: 0.5 m.
- Gravel diameter: 0.03-0.2 m.

 

The mono-pile (4-m diameter and 5-cm material thickness) were driven through the mattress to the planned depth (approx. 25 meters).

 

The transition piece (complete with pre-installed features such as boat landing arrangement, cathodic protection, cable ducts for sub-marine cables, turbine tower flange, etc.) were cast together with the mono-pile. 

The transition piece made it possible to raise the towers to a completely vertical position even if the foundation were not completely level.

 

The cable ducts for the sub-marine cables were closed. The concrete is left to cure.

 

The protective gravel mattress was finished with an additional layer of gravel and stones.

- Thickness: 0.8 m.
- Gravel diameter: 0.350-0.550 m.

 

Erection of the wind turbine and installation of 36-kV cables to substation.
Pile driving
Specially designed barges with a heavy-duty ram were used to drive the mono-pile into the seabed.

 

A typical pile-driving ram. The transition piece were attached to the mono-pile in a special concrete casting process. The top rim of the transition piece is a flange that accommodates bolting of the turbine tower.